Steel bridge of The Metropolitan Expressway (welded joint between longitudinal trough rib and orthotropic deck plate )

1.Field of application

The bayshore Route of The Metropolitan Expressway, Japan.

2.Circumstances of repair

Fatigue cracks were detected on welded joints between longitudinal trough rib and orthotropic deck plate after 15 years of service.

3.Types of structure

The outline of the bridge structure is as follows.

4.Details of loading

Fluctuating loads due to highway live load.

5.Description of damage

Fatigue cracks were detected on welded joints between longitudinal trough ribs and orthotropic deck plates(Fig.1).

File not found: "sfrc01.jpg" at page "事例1"[ź]

Fig.1 Crack location

Cause of fatigue cracks was as follows:

6.Repair method applied

Emergency repair

Stop holes were drilled at the crack tips(Fig.2).

File not found: "stop_holes_sfrc.jpg" at page "事例1"[ź]

Fig.2 Stop holes


Permanent repair

The SFRC pavements were constructed on the orthotropic deck plates instead of asphalt pavements.(Fig.3,Fig.4,).

File not found: "sfrc02.jpg" at page "事例1"[ź]

Fig.3 Construction circumstance of SFRC pavements


File not found: "sfrc03.jpg" at page "事例1"[ź]

Fig.4 The standard cross section of the SFRC pavements