Jhojuin Br. (connection plates between floor beams and truss chords)

1.Field of application

Steel bridge of The Hanshin Expressway, Japan.

2.Circumstances of repair

Fatigue cracks were found in the coped end of the plate girder in 1981 after 13 years of service.

3.Types of structure

The outline of the bridge structure is as follows.

Elevation and cross section are shown in figure 1. The number of the main girders which are deep at 2.2 m are six.

File not found: "copede21.gif" at page "Jhojuin Br. (connection plates between floor beams and truss chords)"[ź]

Fig.1 Elevation and cross section


4.Details of loading

Fluctuating loads due to highway live load.

5.Description of damage

Fatigue cracks were found in the coped ends of the main girders (Fig.2). As a result, fatigue cracks were also found in the coped end for some other bridges with the same structure.

Cause of fatigue cracks was as follows:

6.Repair method applied

Repair and strengthening of parts subjected to cracking were performed by full penetration weld and bolt connection with rib plates (Fig.3).

File not found: "copede3.jpg" at page "Jhojuin Br. (connection plates between floor beams and truss chords)"[ź]

Fig.3 Bolt connection